Westgate Tunnel – Support

  • Location

    2 Somerville Road, Yarraville

  • Builder

    CPBJH Joint Venture

WHY US

M Squared Infrastructure has been a key partner in supporting CPBJH on the Westgate Tunnel Project.

M Squared Electrical has collaborated with CPB-JH on the West Gate Tunnel project, working collaboratively across multiple facets of site establishment, tunnelling, and electrical infrastructure.

As the contractor of choice for CPBJH, we have played a key role in:

  • Site establishment
  • Tunnel Boring Machine (TBM) assembly and disassembly
  • TBM ancillary services installation
  • Machinery maintenance
WHAT

Site establishment and infrastructure have been completed.

Read more
  • Complete site establishment, including:
  • Crib and site amenities
  • 300-person project office complex & community centre
  • 24,000 m² spoil shed, bathhouse, and laundry
  • Installation and wiring of two 15-meter Herrenknecht Tunnel Boring Machines (TBMs)
    • 20 MVA installed TBM power
    • 6 MVA installed TBM services power
  • Installation and management of High Voltage (HV) reticulation systems
  • 600m x 1.8m diameter pipejack drive – pipejack & slurry plant assembly, disassembly, and 24/7 electrical maintenance
  • 6km Marti Technik Tunnel conveyor system, including loop take-up and overland conveyor systems
  • Dismantling and reassembly of three Eilbeck cranes (500T, 250T, 40T)
  • 1,100 kW Tunnel Ventilation System
  • Industrial & potable water pump systems and controls
  • Project-wide emergency lighting & flood lighting, ensuring compliance with AS3012 requirements
  • Installation of three 1MVA integrated backup generator systems
  • Eight 180kW compressor stations to support TBM compressed air interventions
  • On-site support teams for compressed air interventions
  • Tunnelling & Electrical Installations
  • Construction wiring throughout tunnel sites, including:
    • Underground lighting & evacuation systems
    • Construction boards, test & tag services
  • Installation of permanent MEI cable ladder & conduit systems
  • Deployment of site fibre, IT networks, and Wi-Fi systems
  • Installation of 24 km underground leaky feeder systems and P25 Motorola emergency services radio network
  • Tunnelling site dewatering systems & water treatment plants
WHAT

Site establishment and infrastructure have been completed.

Read more
  • Complete site establishment, including:
  • Crib and site amenities
  • 300-person project office complex & community centre
  • 24,000 m² spoil shed, bathhouse, and laundry
  • Installation and wiring of two 15-meter Herrenknecht Tunnel Boring Machines (TBMs)
    • 20 MVA installed TBM power
    • 6 MVA installed TBM services power
  • Installation and management of High Voltage (HV) reticulation systems
  • 600m x 1.8m diameter pipejack drive – pipejack & slurry plant assembly, disassembly, and 24/7 electrical maintenance
  • 6km Marti Technik Tunnel conveyor system, including loop take-up and overland conveyor systems
  • Dismantling and reassembly of three Eilbeck cranes (500T, 250T, 40T)
  • 1,100 kW Tunnel Ventilation System
  • Industrial & potable water pump systems and controls
  • Project-wide emergency lighting & flood lighting, ensuring compliance with AS3012 requirements
  • Installation of three 1MVA integrated backup generator systems
  • Eight 180kW compressor stations to support TBM compressed air interventions
  • On-site support teams for compressed air interventions
  • Tunnelling & Electrical Installations
  • Construction wiring throughout tunnel sites, including:
    • Underground lighting & evacuation systems
    • Construction boards, test & tag services
  • Installation of permanent MEI cable ladder & conduit systems
  • Deployment of site fibre, IT networks, and Wi-Fi systems
  • Installation of 24 km underground leaky feeder systems and P25 Motorola emergency services radio network
  • Tunnelling site dewatering systems & water treatment plants
WHAT

Our commitment to quality, safety, and efficiency ensures smooth project execution while minimising downtime.

Read more

Project Statistics

  • $15 billion mega-project
  • 6 km of tunnels
  • 20 MW of installed excavation equipment

Specialised Technical Expertise


Shift Technicians for Herrenknecht 15-meter TBM assembly, wiring, testing, and commissioning alongside Herrenknecht technicians.

 

Shift Maintenance Technicians supporting:

  • Tunnel excavation
  • Assembly & disassembly of TBMs
  • Back-end works for 10 Euroform backup gantries, including:
  • Robotic drill rigs (scabbling & drilling gantries)
  • Reinforcement & corbel casting gantries
  • MEI permanent cable ladder, drainage, fire & dewatering systems installation
  • Road deck plank installation gantry
  • CREG Cross Passage Machines:
  • 21 assemblies & 21 disassembly’s
  • Modifications, instrumentation testing, commissioning, and maintenance
  • Permanent Works & Project Support
  • High Voltage (HV) earthing
  • Reinforcement earth bonding
  • Pit & conduit installation
  • Cable ladder installations
WHAT

Our commitment to quality, safety, and efficiency ensures smooth project execution while minimising downtime.

Read more

Project Statistics

  • $15 billion mega-project
  • 6 km of tunnels
  • 20 MW of installed excavation equipment

Specialised Technical Expertise


Shift Technicians for Herrenknecht 15-meter TBM assembly, wiring, testing, and commissioning alongside Herrenknecht technicians.

 

Shift Maintenance Technicians supporting:

  • Tunnel excavation
  • Assembly & disassembly of TBMs
  • Back-end works for 10 Euroform backup gantries, including:
  • Robotic drill rigs (scabbling & drilling gantries)
  • Reinforcement & corbel casting gantries
  • MEI permanent cable ladder, drainage, fire & dewatering systems installation
  • Road deck plank installation gantry
  • CREG Cross Passage Machines:
  • 21 assemblies & 21 disassembly’s
  • Modifications, instrumentation testing, commissioning, and maintenance
  • Permanent Works & Project Support
  • High Voltage (HV) earthing
  • Reinforcement earth bonding
  • Pit & conduit installation
  • Cable ladder installations

Leave a Reply

Your email address will not be published. Required fields are marked *